Local Highway Construction for the Week of June 28

North Central Ohio – Here is a look at construction projects that are anticipated to impact highways in Erie, Huron, Lorain, Ottawa, Sandusky, and Seneca Counties on the week of June 28.

Erie County

SR 113 will be closed Tuesday, July 6 between River Road and McIntyre Road for 60 days. The detour route for eastbound motorists will be SR 113 to U.S. 250, north on U.S. 250 to SR 13, north on SR 13 to SR 2, east on SR 2 to SR 61, south on SR 61 to SR 113. It is reverse for westbound motorists.

Huron County

State Route 13 between SR 162 and Omega Road will have daily lane closures for a culvert replacement project. The project is estimated to be completed in July.

State Route 162 between Greenwich East Town Line Road and Euclid Road will close on Tuesday, July 6 for a culvert replacement project. The detour route for westbound motorists will be SR 162 to SR 60, south on SR 60 to U.S. 224, west on U.S. 224 to U.S. 250, north on U.S. 250 to SR 162. It will be reverse for eastbound motorists. The project is estimated to be completed on Wednesday, August 4.

Lorain County

U.S. 20 at the structures over Grafton Road and SR 57 will have lane closures for bridge repairs. Traffic will be maintained eastbound and westbound with portable concrete barriers or construction barrels. The lane closures may occur concurrently or alternately depending on project work.

Ottawa County

State Route 163 between Hartshorn Rd and Skyline Dr in Lakeside and Marblehead may experience lane restrictions.

State Route 579 between the Wood County line and State Route 2 in Williston will continue to experience lane restrictions for resurfacing. The project is expected to be completed in in June.

Lane restrictions are possible county-wide for a sign and post replacement project through October.

Sandusky County

Eastbound U.S. Route 20 between State Street and US 6 in Fremont will be closed for a slope repair. The project is expected to be completed in August. The detour is to go from US 20 to SR 590 to US 6 to US 20

Westbound U.S. Route 6/20 between SR 19 and US 20 in Fremont will be reduced to one lane for a slope repair. The project is expected to be completed in August.

State Route 19, between Maple Ln. and Academy St. in Green Springs is closed for a culvert replacement. The project is expected to be completed in August. The detour is to go from SR 101 to SR 510 to US 20

State Route 53, between Schwartz Rd. and the Ohio Turnpike in Fremont may experience lane restrictions for Turnpike work. The project is expected to be completed in September.

Seneca County

U.S. Route 23 between Wyandot County and Fostoria will experience lane restrictions for resurfacing and guardrail. The project is expected to be completed in October.

State Route 53 between Highland Park Estates and Cottage Dr in Tiffin will experience lane restrictions for resurfacing beginning Monday, August 3. The project is expected to be completed in September.

State Route 100, between County Road 58 and Riverside Dr in Tiffin will experience lane restrictions for resurfacing beginning Monday, July 12. The project is expected to be completed in November.

SR 100 between Township Road 58 and Township Road 17 will be closed for bridge repair from July 27 to July 29. The detour is to go from SR 67 to US 224 to SR 100